How often should alternate exits caused by an ILSM plan be inspected during construction?

  1. Weekly

  2. Monthly

  3. Daily

  4. At the end of construction

The correct answer is: Daily

Alternate exits created due to an Interim Life Safety Measures (ILSM) plan are crucial for maintaining safety during construction activities, particularly in healthcare facilities where the safety and well-being of patients, staff, and visitors are of utmost importance. Given the dynamic environment of construction, it is essential to monitor these exit routes frequently. Daily inspections are warranted to ensure that these temporary exits are safe, unobstructed, and functional. This frequency allows for the identification and rectification of potential hazards that may arise each day due to ongoing construction work. Regular monitoring helps to maintain compliance with safety regulations and best practices, thus fostering a safer environment for everyone involved. Other options suggest longer intervals between inspections, which may increase the risk of overlooking hazards or issues that could compromise safety. Therefore, the daily inspection aligns with the overall goal of the ILSM plan to provide safe pathways and responsive management of risks during the construction process.